Migration Process

Following is i2i migration process;

1. PLAN:

  1. Define multiple possible migration strategies
  2. Data profiling
  3. Data mapping
    1. Current applications (data structures, identify critical validation points)
    2. Current infrastructure (HW, Database)
    3. Define future infrastructure requirements
  4. Determine migration requirements
  5. Determine final migration strategy
  6. Create migration project plan and mobilize resources
  7. Create migration architecture
  8. Develop test plans and acceptance criteria

2. MIGRATE:

  1. Develop/configure migration scripts
  2. Run pre-validation tests
  3. Data Extraction
  4. Data Assessment
  5. Data Alignment
  6. Data Load
  7. Verify migration completion

3. VALIDATE:

  1. Run post-validation tests
  2. Perform knowledge transfer
  3. Create report on migration statistics
  4. Migration close out meeting